Master plans

Phase 1 (European ‘best-in-class‘ level in quality, service and efficiency)

  • Increase in 60% the beer plant capacity to consolidate all beer and sidra volume in one plant in Portugal
  • Modernize the plant, throughout the best technical solutions in the market, searching always for the highest automation level, complying with all health & safety requirements, leveraging the quality of products and archiving the best kpi’s of the industry in terms of efficiency, losses and utilities consumptions.
  • Team (68 people involved – 38 full time, 38 companies contracted and Steering Committee with 9 members from Directions and Board)

Phase 2 (Increase the plant capacity to 6 Mhl)

  • Increase in 20% the beer plant capacity
  • Install a new NRGB line (60.000 bph @ 200 ml / 250 ml / 330 ml) and increase 30% the existing keg line (from 600 kegs7hour to 720 kegs/hour @ 30L kegs)
  • Install new bright beer tanks
  • Develop a deep study to define a future solution to 6 Mhl capacity and the what could be the maximum expansion capacity and how to grow

Phase 1

  • Geophysics study of the region to identify potential new sources of water and install 3 new water’s boreholes
  • Increased in 25% the plant capacity in 12 months
  • Modify the image of flavor water sku’s, installing a machine to apply sleeves and modify the line layout to work with both options, label and sleeve
  • Retrofit a complete dry area with available equipment from stopped plants to split PET and glass line increasing filling capacity and OEE
  • Team (12 people, 9 companies contacted and Steering Committee with 5 members from Directions and Board)

Phase 2

  • Build up 3 new water’s boreholes
  • Increase in 45% the plant capacity in 3 years
  • New combined line 60.000 bph
  • Increase capacity and modernize Utilities area
  • Full automated system in the whole process area, from the water reception tanks, through the water treatment and final water storage tanks for filling área
  • Increase logistic capacity and improve finish goods flow, packaging material access into the lines and trucks loading area
  • New laboratory
  • New social area and amenities

Consolidate the entire cheese / whey production volume in one plant

  • Cheese plant:
    • 20.000 m² of construction
    • 3.000 kg/h production
    • Cold storage: 6.500 pallets positions / 11 loading bays
  • Whey plant
    • 3.500 kg/h production
    • 2.000 pallets positions / 2 loading bays
  • New plant with the best technical solutions concerning the highest automation level, health & safety requirements compliance and quality of products guarantee

Proved Experience

Your ideas - our challenges

Projects

Our background

Back
WE ARE 
_able